PA DEP – Friends of Glen Providence Park https://glenprovidencepark.org Preserving and enhancing Delaware County's oldest park Tue, 25 Apr 2017 18:02:48 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.1 Broomall’s Dam Removal https://glenprovidencepark.org/2017/04/25/broomalls-dam-removal/ https://glenprovidencepark.org/2017/04/25/broomalls-dam-removal/#comments Tue, 25 Apr 2017 17:59:53 +0000 http://glenprovidencepark.org/?p=6903 With Broomall’s Dam scheduled to be partially removed in the near future, we thought it was relevant to provide an in-depth recap of the February meeting with the PA Department of Environmental Protection (DEP), who will be managing the planned breach.

On February 22, about 100-150 people crowded into the Media Borough Parlor Room to meet with officials from the PA Department of Environmental Protection (DEP) to discuss the planned partial breach of Broomall’s dam in late April.

After some time to look over the technical plans and respond to residents’ questions, the DEP presented the why’s and how’s of the removal of Broomall’s Dam for safety reasons. Roger Adams, Division Chief of Dam Safety, gave a compelling presentation of the dangers to human life and property when a dam fails. Examples include the Bayless Dam, in which 10” of rain caused a catastrophic failure.

High hazard dam in poor condition

Of the 3,371 dams in Pennsylvania, only 754 are high hazard dams. While Broomall’s Dam is smaller than large dams like the Youngstown Dam, it is still categorized as a High Hazard C-2 dam, based on the amount of water and sediment held back and the height. It is also a High Hazard dam in poor condition. Even if the dam is rebuilt, it will again be a High Hazard C-2 dam.

Broomall’s an orphan dam that is deteriorating

Duke Adams (no relation to Roger), took up the presentation and discussed the issues around ownership. The dam was built in 1883 by John Broomall for ice harvesting. In 1980 the Army Corps of Engineers found the dam to be structurally in poor condition. In 1996 the roadway was closed for safety reasons. No party, not Broomall’s Lake Country Club (BLCC), Media Borough or Delaware County have been willing to take up the maintenance responsibilities over this time. The DEP has considered Broomall’s Dam an “orphan dam” because of the lack of responsible or willing owner.

In June 2014, Delaware County, BLCC and Media Borough signed a stipulation and order. Duke Adams explained that this order means that Media Borough would manage the reconstruction of the dam, and Delaware County would take ownership of the downstream face, and BLCC would be the owner and responsible party for the upstream face.

In 2012, BLCC sued Media Borough over its plan for a one-lane compromise for the bridge  — a solution that was supported by borough residents, Friends of Glen Providence Park, and the majority of Borough Council. Shortly thereafter the dam began to deteriorate significantly, with entire pieces of wall crumbling on the upstream and downstream side. The DEP elected to lower the water level to its absolute minimum in June 2013, and when the lake level was not maintained, the DEP returned and lowered it again in March 2016.

Eliminate the hazard

However, due to continual delays and a lack of clarity of an owner (none of the three parties has stepped forward and take responsibility to date), the DEP has decided to eliminate the hazard of the dam. By removing nearly all of the standing water and a significant amount of liquid sediment, the pressure on the dam walls will be reduced. The hazard category will be lowered to C-4.  Their presentation highlighted the dangers of allowing high hazard dams to remain in place.

Work begins in early May

The work on the dam will begin around May 9th and should conclude within two months. During construction, the entire corner of 3rd and West Street will be closed to all traffic and the entrance to BLCC swim club will be closed, to reopen once the partial breach is complete.

The main spillway of the dam will be removed, as will the waterfall. Broomall’s Lake will drain almost completely and construction access into the lake will remain until the dam is reconstructed. The original stream of Broomall’s Run will find its own course and several springs that feed into Broomall’s Lake may make their appearance.

The DEP reported that before dam removal begins, up to two weeks will be spent to remove the PA Threatened Northern Redbelly Turtle (Pseudemys rubriventris) and native snapping turtles, which will be relocated to the pond in Glen Providence Park. The invasive Red-eared slider (a similar looking turtle) will be removed and donated to science programs. Other fish, frogs and invertebrates will have to find their way during the draining of the lake or they will perish. Traps to capture turtles were set on April 24th. 

Loss of pedestrian and bicycle access for Upper Providence for 2 years or more

The likely reason why so many people came to the meeting was due to the disruption of pedestrian and bicycle access across the dam starting at the end of April, and lasting until the proposed dam reconstruction. Roger Adams could not say how long the period between dam removal and dam reconstruction would be, but did not hesitate to say at least two years. (The dam reconstruction permit has not been approved or scheduled to date.)

There were a number of questions from the audience on the issue, particularly focused on Upper Providence residents who use Third Street frequently to walk into Media. Safety issues were also raised by residents, particularly the concern that if there were no access at all, some daring individuals would somehow find a way that would most likely be very unsafe. The DEP indicated that there might be a possibility of installing a temporary pedestrian bridge.

Stream Restoration

A benefit of dam removal is the re-establishment of open waterways and natural streams. Artificial dammed bodies of water not only present a hazard of failure on the downstream side, but they also hold back aquatic life and sediment that contribute to the overall health of our waterways. 

Pedestrian Bridge

A coalition of Upper Providence and Media neighbors and Friends of Glen Providence Park is working to establish a temporary pedestrian footbridge to maintain the connection between Media and Upper Providence in the time period between dam removal and dam reconstruction. The proposed footbridge is modular and can be relocated into Glen Providence Park at one of the former bridge sites once dam reconstruction begins. If you are interested in supporting this effort, please contact us.

]]>
https://glenprovidencepark.org/2017/04/25/broomalls-dam-removal/feed/ 1
2-22-2017 What’s up with the dam coming down? https://glenprovidencepark.org/2017/02/10/2-22-2017-whats-up-with-the-dam-coming-down/ https://glenprovidencepark.org/2017/02/10/2-22-2017-whats-up-with-the-dam-coming-down/#respond Fri, 10 Feb 2017 21:32:45 +0000 http://glenprovidencepark.org/?p=6866 Public Meeting about 3rd Street & Broomall’s Dam with DEP

On Wednesday, February 22 at 6pm, at the Media Borough Parlor Room, area residents will have an opportunity to hear from the PA Department of Environmental Protection (DEP) in a Public Informational Meeting about the planned partial breach of Broomall’s Dam, currently scheduled for April 30th.

The partial breach will reduce the safety hazard of the orphaned dam which is in severe disrepair.

However, the partial breach will render the road impassable to pedestrians and bicycles in addition to cars for two years or more, until the proposed dam reconstruction is complete. With no parties yet willing to claim ownership of the current or proposed dam, it is uncertain how long this pre-construction phase will last.

If you have questions or concerns about the reasons for the partial dam breach, its impacts to the park, stormwater, or pedestrian access to the park and across 3rd Street, please come to this meeting. This is a rare opportunity to meet with the DEP. Let us know you’re coming by RSVP-ing!

Temporary Pedestrian Bridge?

Friends of Glen Providence Park has requested Media Borough Council to consider the construction of a temporary pedestrian bridge during this pre-construction phase. We feel it is in the best interest of Media Borough and Upper Providence to maintain this connection.

Why maintain the connection:

  • Safety: We are concerned that people will attempt to find a way to cross the breach that is unsafe.
  • Economics: Many people walk to Media for shopping and great events like Dining Under the Stars. Some people commute to work from UP to Media on foot — across Broomall’s Dam on 3rd Street!
  • Community: 3rd Street is a valuable connection between Upper Providence and Media neighbors and activities.
  • Best Practices: It is a PennDOT recommendation in their Design Manual to continue pedestrian access during construction (Chapter 6.14, Pedestrian Facilities and the Americans with Disabilities Act, 2012.).
  • Time: 2-3 years is a long time to have this connection broken.

If you’d like to see a temporary pedestrian bridge, please come to the meeting and make your voice heard.

In addition, it is our understanding that the 3rd Street entrance to the park will be closed while the DEP is removing the dam, which is expected to take about 60 days.

The meeting is on Wednesday, February 22, from 6:00-7:30 at the Parlor Room of the Media Borough Municipal Complex, 301 N. Jackson Street, Media.

 

Be informed! You can read an overview and history of the 3rd Street Project, with links to past articles, in the menu above. And you can learn much more about the 3rd Street project and Broomall’s Dam, and find detailed information about the partial dam removal by reading our past articles in the Dam/Bridge Category – and by exploring the Tags – on the right.

 

Friends of Glen Providence Park continues to support dam removal and stream restoration with an environmentally sensitive connection between Upper Providence and Media, which will minimize damage to the park. 

 

]]>
https://glenprovidencepark.org/2017/02/10/2-22-2017-whats-up-with-the-dam-coming-down/feed/ 0
Broomall’s Dam Update: new Spring date for partial dam breach https://glenprovidencepark.org/2017/01/23/broomalls-dam-update-new-date-for-partial-dam-breach/ https://glenprovidencepark.org/2017/01/23/broomalls-dam-update-new-date-for-partial-dam-breach/#respond Mon, 23 Jan 2017 19:47:37 +0000 http://glenprovidencepark.org/?p=6795 As we previously reported, the PA Department of Environmental Protection decided in October 2015 to schedule a partial breach of Broomall’s Dam (see detailed plans here) to resolve the safety issues of a high-hazard dam in disrepair. While the partial breach had been scheduled for Fall 2016, the start date has been moved back to April 30th, with the construction taking 60 days, according to correspondence between the parties. The updated timing is based on the completion of rerouting of utilities such as telephone, electric, gas, and water.

This is planned as a temporary dam removal until the proposed new dam is built. For details including safety, public notice, and 3rd Street access, see our May 2016 update

 

The Friends of Glen Providence Park continues to support dam removal, stream restoration and a local discussion of an environmentally-sensitive bridge between Media Borough and Upper Providence.

 

]]>
https://glenprovidencepark.org/2017/01/23/broomalls-dam-update-new-date-for-partial-dam-breach/feed/ 0
Broomall’s Dam Update: Temporary Partial Breach this fall https://glenprovidencepark.org/2016/05/23/broomalls-dam-update-temporary-partial-breach-this-fall/ https://glenprovidencepark.org/2016/05/23/broomalls-dam-update-temporary-partial-breach-this-fall/#respond Tue, 24 May 2016 02:36:28 +0000 http://glenprovidencepark.org/?p=6215

As we reported in October 2015, the the PA Department of Environmental Protection (PADEP) will conduct a “temporary partial breach” of Broomall’s Dam this year. This is planned as a temporary dam removal until the proposed new dam is built. By conducting this partial breach, the PADEP is taking action to address the serious safety […]]]>

As we reported in October 2015, the the PA Department of Environmental Protection (PADEP) will conduct a “temporary partial breach” of Broomall’s Dam this year. This is planned as a temporary dam removal until the proposed new dam is built. By conducting this partial breach, the PADEP is taking action to address the serious safety issue posed by the current Broomall’s Dam, which is a high-hazard dam that was declared unsafe in 1980 by the Army Corps of Engineers.  

Timeline

The PADEP originally intended to conduct the partial breach before June 1 this year, but the timeline has been updated. According to Duke Adams of the PADEP Division of Dam Safety, PECO will re-route the gas lines that currently run through the dam by July. Both the gas and water lines that run through the current dam will be permanently re-routed – the proposed new dam would not have utilities running through it.

The PADEP will begin the partial breach in September, and the process should take 6 to 8 weeks. This would mean that the breach should be complete by Thanksgiving. Based on the timing of the dam permit process, the PADEP indicated we are “probably 2 years off from construction” of a new dam – which would take us to spring 2018 for construction of the proposed new dam to begin.

What the partially breached dam will look like

"Preliminary" plan

“Preliminary” plan

Officials at the PADEP explained that the top layer of the current dam, including the roadway, will be removed – the resulting structure will be a smaller dam 10 to 12’ lower than the current dam. Upstream of the dam will be a stream in place of the current Broomall’s Lake – the PADEP will allow the stream to find its own channel. In the growing season, the new streambanks should fill quickly with vegetation. During the breach process this fall, there will be a dirt road causeway built upstream for construction access, but it is undetermined if that will remain until construction starts on the new proposed dam.

According to the PADEP, the stream will pass over the lower dam through a flow channel notched out of the top of the dam – there will be a waterfall lower than the current one. Downstream of the dam, there will be some riprap on the park side near the stream, but there will be minimal disturbance to the park. The PADEP indicated that only a few trees closest to the top of the dam will be removed when they take the level down. You can review the pdf of the PADEP’s preliminary partial breach plans, and pdf’s and images are also at the bottom of this article.

Park Access & 3rd Street Access

Officials at the PADEP advised that construction equipment will be staged at the 3rd Street entrance, so the 3rd Street entrance to Glen Providence Park will be closed when they are breaching the current dam, from approximately mid-September through Thanksgiving. The entrance will be open again after the current dam is breached, until construction of the new proposed dam would begin.

As currently planned by the PADEP, there will be barricades on both sides of the dam at 3rd Street – there would be no access for pedestrians or bikers until the proposed new dam is completed. As it is likely 2 years until construction begins, it could mean 3 years without access to cross Broomall’s Run at 3rd Street. Friends of Glen Providence Park has inquired with PADEP and Media Borough Council about constructing a footbridge to cross Broomall’s Run over the lowered dam. We will continue to advocate for a footbridge to allow pedestrian and bike access, keeping the Upper Providence and Media Borough communities connected.

Safety

According to the PADEP, if the partially breached dam fails, sediment would “slowly ooze” – there should not be danger to those in park. In addition, the partially removed dam will have a wider (more stable) base than the current one. The partially breached dam will be classified as C4, meaning there would be no potential loss of life or “public convenience” (road/traffic).   

Public notice & public meeting

We asked the PADEP to post signs well in advance of construction advising of the 3rd Street closure and park entrance closure. We also requested a public meeting with the PADEP about the partial dam breach process, similar to the Dam Safety Workshop we hosted in August 2012, so the community can be fully informed and have their questions about the breach process addressed.  

Emergency Action Plan signatures

It is our understanding that there are still no signatures on the Emergency Action Plan (EAP) for the proposed new dam, which is required to obtain a dam permit. The PADEP indicated, “There will be no authorization to build [a new dam] until there are signatures.” In July 2015, Media Borough Council passed a resolution that they would not sign the EAP for the proposed dam. As owners and operators of the proposed new dam under the Stipulation Agreement, it is expected that Delaware County and Broomall’s Lake Country Club would sign it.

 

You can read about and see pictures of the proposed 1.1 acre construction area for the proposed new dam, including the approximately 2/3 acre of Glen Providence Park that would be buried under earthfill, in our 1.1 Acre Photojournal.

The Friends of Glen Providence Park continues to support dam removal, stream restoration and a local discussion of an environmentally-sensitive bridge between Media Borough and Upper Providence.

Click on the green link to view the PDF of the PADEP’s preliminary partial breach plans, or view the images below:

 

]]>
https://glenprovidencepark.org/2016/05/23/broomalls-dam-update-temporary-partial-breach-this-fall/feed/ 0
Broomall’s Dam Update: PennDOT Funding https://glenprovidencepark.org/2015/11/14/broomalls-dam-update-penndot-funding/ https://glenprovidencepark.org/2015/11/14/broomalls-dam-update-penndot-funding/#respond Sat, 14 Nov 2015 17:38:55 +0000 http://glenprovidencepark.org/?p=5963 PennDOT May Not Pay for Dam Replacement if a Bridge is Less Expensive

Responding to the decision by the Pennsylvania Department of Environmental Protection (PA DEP) to breach Broomall’s dam by June of 2016, Timothy Stevenson, Design Portfolio Manager for District 6 of the Pennsylvania Department of Transportation (PennDOT), announced that PennDOT was not willing to fully fund the reconstruction of the dam if the alternate option of building a bridge proved to be less expensive.

In an e-mail sent to PennDOT contractor Sidney New on October 16, 2015, and copied to Media Borough and Delaware County, Mr. Stevenson noted that the project’s draft environmental document identified two primary needs: 1) addressing transportation network deficiencies and 2) resolving unsafe dam conditions. “The DEP’s proposed action [to breach the dam] should resolve the second need for the project, leaving only the first need to be addressed,” wrote Stevenson.

Citing a lack of adequate funding to address all of the region’s current bridge repair needs, Stevenson stated “…I cannot approve additional expenditures beyond what is needed to address the transportation network deficiencies…should the cost [of dam replacement] exceed the cost of a bridge, I can only see A-183 funds [Local Bridge Funds] being applied to a prorated portion of the total project costs.”

Click to read the entire October 16 email from PennDOT.

In a subsequent telephone conversation with a representative of the Friends of Glen Providence Park, Mr. Stevenson confirmed PennDOT’s intention to only provide prorated funding for the amount of the cheapest option (e.g. if dam replacement cost $3 million dollars and constructing a bridge cost $2 million dollars, PennDOT would only pay out $2 million. The same formula would apply if dam replacement proved to be cheaper than constructing a bridge).

Mr. Stevenson’s e-mail leaves many questions unanswered. 1) What bridge design will be used as the basis for a cost comparison with dam reconstruction? 2) Who will conduct an independent cost analysis? 3) If a cost analysis did determine that building a bridge was the less expensive option, would a dam still be constructed? 4) If yes, which party (or parties) would pay the balance between PennDOT funding and the full cost of dam replacement?

The Friends of Glen Providence will be seeking answers to these and other questions that arise regarding the now uncertain funding plan for the Broomall’s dam project.

Friends of Glen Providence Park continues to believe that dam removal, stream restoration, and a community conversation regarding an environmentally sensitive bridge between Media Borough and Upper Providence Township is the best course of action.

]]>
https://glenprovidencepark.org/2015/11/14/broomalls-dam-update-penndot-funding/feed/ 0
Broomall’s Dam Update: temporary dam removal https://glenprovidencepark.org/2015/10/15/broomalls-dam-update-temporary-dam-removal/ https://glenprovidencepark.org/2015/10/15/broomalls-dam-update-temporary-dam-removal/#comments Fri, 16 Oct 2015 02:30:18 +0000 http://glenprovidencepark.org/?p=5826 As reported by Media Borough Council President Brian Hall at tonight’s Council meeting, the PA Department of Environmental Protection (PADEP) has indicated that they will conduct a “partial breach” of Broomall’s Dam by June 1, 2016. The PADEP has had growing concerns about the structural integrity of the aging dam, which was determined to be in poor condition in 1980. This would be a temporary dam removal until the dam is replaced as “part of overall efforts to reestablish the dam and roadway.”

The PADEP communicated their intention to breach the dam at a meeting on Wednesday, October 14 between representatives of Delaware County, Media Borough, Broomall’s Lake Country Club, and the PADEP. That meeting was to resolve issues surrounding who would sign as owner(s) for the Emergency Action Plan(s) for Broomall’s Dam, which is to plan for public safety in the event of an accidental dam failure. The meeting was also to address other responsibilities surrounding the operation and maintenance of Broomall’s Dam.

As we previously reported, Media Borough voted in July not to sign the EAP as owner. Hall reported tonight that there is “still some wordsmithing about responsibilities under the EAP,” the “terms are not worked out,” and “no one has set ink to paper” to sign as owner.

According to Hall, while the dam is temporarily breached, there will be no foot traffic across Broomall’s Run to and from Upper Providence. There might also be restrictions in the north end of Glen Providence Park. This may last a few years, until construction of the new dam is complete – and according to an update from Schnabel Engineering this April, construction on the new dam would likely begin in 2017 or 2018.

We would like to learn more about this project, including environmental impacts to Glen Providence Park and Broomall’s Run, whether there will be access to Glen Providence Park from the entrance at 3rd & West Streets, and whether there is any way to create access for pedestrians to cross to and from Upper Providence. As we learn the answers to these questions, we will post updates.

You can read about and see pictures of the proposed 1.1 acre construction area for the new dam, including the approximately 2/3 acre of Glen Providence Park that would be buried under earthfill, in our 1.1 Acre Photojournal.

The Friends of Glen Providence Park continues to support dam removal, stream restoration and a local discussion of an environmentally-sensitive bridge between Media Borough and Upper Providence.

]]>
https://glenprovidencepark.org/2015/10/15/broomalls-dam-update-temporary-dam-removal/feed/ 1
Broomall’s Dam Update: Ownership & Emergency Action Plan https://glenprovidencepark.org/2015/07/20/broomalls-dam-update-ownership-emergency-action-plan/ https://glenprovidencepark.org/2015/07/20/broomalls-dam-update-ownership-emergency-action-plan/#respond Mon, 20 Jul 2015 18:50:34 +0000 http://glenprovidencepark.org/?p=5609 On Thursday, July 16th, the seven members of Media Borough Council voted unanimously for a resolution declaring that the Borough was not the owner of Broomall’s Dam located on Third Street, next to Glen Providence Park.  The resolution gave approval for the Borough to sign the Pennsylvania Department of Environmental Protection’s (PA DEP) Emergency Action Plan (EAP) as the dam operator during the construction phase – but not to sign the ownership line of the required document as the dam owner. The vote was met with applause from a full audience.

The EAP is a formal document that describes procedures to minimize the risk of loss of life and property damage when potential emergency conditions threaten a High Hazard Potential Category 1, 2 or 3 dam. PA DEP has identified Broomall’s Dam as a Category 2 High Hazard dam.  The Dam Safety and Waterway Management Act (Subchapter B 105.34)  states that the owner(s) of a high hazard dam must sign the ownership line of the document.  A properly signed and executed EAP is required for the PA DEP to issue a dam construction permit.

The ownership of the dam has been the subject of legal dispute between Broomall’s Lake Country Club, Delaware County, and Media Borough since 2006, following decades of inaction to repair or replace the dam, due to ongoing ownership questions since Broomall’s Dam was declared unsafe by the Army Corps of Engineers in 1980.

The 2011 Stipulation and Order signed by all three parties assigned tasks and responsibilities regarding the construction and maintenance of the proposed replacement dam and roadway on top of the dam. However, the Stipulation and Order did NOT resolve the issue of ownership.

While Media Borough Council has clarified that it will not sign the ownership line of the EAP, there have been no public statements or documents released by Broomall’s Lake Country Club or Delaware County that indicate if one or both of those parties will sign the ownership line of the EAP.

Media Borough Council also authorized the Borough to sign the dam construction permit application at the July 16th meeting, while adding an addendum that stated that signing the permit did not constitute any claim of ownership of Broomall’s Dam by the Borough.

 

The Friends of Glen Providence Park continues to support dam removal, stream restoration and a local discussion of an environmentally-sensitive bridge between Media Borough and Upper Providence.

]]>
https://glenprovidencepark.org/2015/07/20/broomalls-dam-update-ownership-emergency-action-plan/feed/ 0
Third Street Update & Dam Construction Timeline https://glenprovidencepark.org/2015/04/10/third-street-update-dam-construction-timeline/ https://glenprovidencepark.org/2015/04/10/third-street-update-dam-construction-timeline/#respond Sat, 11 Apr 2015 00:35:08 +0000 http://glenprovidencepark.org/?p=5353 John Harrison from Schnabel Engineering gave an update on the Third Street project at the Media Borough Council Workshop meeting on Thursday, April 2. He gave an overview and rough timeline for the upcoming design and construction for the new Broomall’s Dam.

PennDOT confirmed funding of the project the previous week, so Schnabel is now working on updating the dam design. Larson Design Group will design the roadway, box culvert, and stormwater system that goes under road. Schnabel and Larson will work together, and consult with the PA Department of Environmental Protection (PADEP), PennDOT, and the Army Corps of Engineers on various aspects of the project.

Wetlands

Schnabel will seek approval from the Army Corps and PADEP of the wetlands mitigation site. Because wetlands in Glen Providence Park would be destroyed* for the dam construction project, it is required that a comparable area of wetlands be established elsewhere (referred to as “wetland swapping”). Schnabel proposes converting the upstream part of the park’s pond, and the flat area upstream of that, into a wetland (as we have written about in Upcoming Changes: Pond & Wetlands).

Aesthetics

A landscape architect from Larson will work on the aesthetics of the new dam. Mr. Harrison indicated the new spillway (waterfall) will not be that visible, but that the box culvert on the downstream side will be a big structure and very visible – they plan a design using form liners so that any exposed concrete looks like stone. They also propose black metal fencing as a more attractive alternative to a cyclone fence to protect the 20 foot drop. The PA DEP does not allow any trees or shrubs on the dam slope, so the fence and large culvert would be quite visible within Glen Providence Park and from the Third Street park entrance. There may be opportunity for public input into the aesthetics.

Time frame

  • According to Larson, the design process should take 18 months from now to final design – which would take us to October 2016.
  • Then Schnabel says the DEP will take 6 months to a year for approval, which would put final approval sometime between April and October 2017.
  • According to a June 13, 2011 PA Fish & Boat Commission Letter, “any construction activities affecting the waterway should take place between April 15 and October 15 in order to allow turtles to avoid the project area while they are active.”
  • Depending on the timing of PADEP approval, construction could start as soon as April 2017, or as late as April 2018 – likely finishing in 2018 or 2019.
  • Council asked Schnabel to give a brief status of the project monthly that could be posted on the Borough website.

*You can read about and see pictures of the proposed 1.1 acre construction area for the new dam, including the approximately 2/3 acre of Glen Providence Park that would be buried under earthfill, in our 1.1 Acre Photojournal.

The Friends of Glen Providence Park continues to support dam removal, stream restoration and a local discussion of an environmentally-sensitive bridge between Media Borough and Upper Providence.

]]>
https://glenprovidencepark.org/2015/04/10/third-street-update-dam-construction-timeline/feed/ 0
3rd Street Update & Broomall’s Dam Safety https://glenprovidencepark.org/2014/04/24/3rd-street-update-broomalls-dam-safety/ https://glenprovidencepark.org/2014/04/24/3rd-street-update-broomalls-dam-safety/#respond Fri, 25 Apr 2014 02:45:41 +0000 http://glenprovidencepark.org/?p=4282 There was no resolution to the 3rd Street Litigation at the March 31 conference before Judge Proud,with Media Borough, Broomall’s Lake Country Club (BLCC) and Delaware County. There is a hearing with Judge Proud scheduled for Friday, May 9, at 9:30am in court room #10 at the Court House in Media. According to Judge Proud’s office, the hearing is open to the public – we will report on the outcome of that hearing.

As mentioned this week in a Delaware County Times article, in September 2012, Media Borough Council had voted to move forward with the design of a new dam to include a one-way eastbound road (with width to accommodate two lanes). This was after a 15-month public participation process involving at least 4 public meetings, a public survey, and extensive work by a Citizen Advisory Committee.

In response, BLCC filed a Petition for Contempt in October 2012, after which Judge Proud revoked the Stipulation Agreement in February 2013. The Commonwealth Court reinstated the Stipulation Agreement in December 2013, remanding the case to Proud’s jurisdiction. The May 9 hearing will be 20 months since the Petition for Contempt was filed, halting further progress.

Broomall’s Dam Safety: There is a gas line running through Broomall’s Dam, which would pose a public and environmental threat if the dam were to fail. After we asked the PA Department of Environmental Protections (PA DEP) about this in January, the PA DEP contacted PECO. This week, PECO has been working to install a safety valve for the gas line, so that it can be shut off in case of an emergency with the dam.

The Friends of Glen Providence Park continues to support dam removal, stream restoration and a local discussion of an environmentally-sensitive bridge between Media Borough and Upper Providence.

]]>
https://glenprovidencepark.org/2014/04/24/3rd-street-update-broomalls-dam-safety/feed/ 0
Update: PA DEP & Broomall’s Lake Water Level https://glenprovidencepark.org/2013/11/22/update-pa-dep-broomalls-lake-water-level/ https://glenprovidencepark.org/2013/11/22/update-pa-dep-broomalls-lake-water-level/#respond Fri, 22 Nov 2013 22:05:49 +0000 http://glenprovidencepark.org/?p=3986 As we previously reported, on June 12 this year, Pennsylvania Department of Environmental Protection (DEP) siphoned water from Broomall’s Lake. This was because the water was not being kept at a lowered “drawdown” level – in violation of multiple requests by the DEP since December 2009. The lake remained lowered until mid-July, when it returned to full level- and has remained at full level since.

Posted by DEP in June 2013, disappeared in July 2013.

Posted by DEP in June 2013, disappeared in July 2013. Click for a closer view to read it.

 

Notice of Action

After siphoning the lake, the DEP posted this notice explaining that the water level was lowered because the dam “is in unsafe condition.” It also explains that “any intentional vandalism, obstruction, or tampering with this drawdown system” is punishable “by fines of up to $1,000 per offense and/or imprisonment for up to 60 days.” Sometime in early July, this sign disappeared.

 

Visual barrier

This visual barrier was installed by BLCC on July 19

This visual barrier was installed by BLCC on July 19

On July 19, for unknown reasons, BLCC put up a visual barrier of black sheeting along the fence, which blocked the view of the lake from the road.

 

Water level

By July 24, the lake had returned to full level, with water coming over the spillway- and it has remained at full level since. When the lake is drawn down, the water should only come through the pipe. When the water comes over the spillway, the lake water level is too high.

 

The lake was back to full level by July 24, with water coming over the spillway.

The lake was back to full level by July 24, with water coming over the spillway.

DEP response to raised water level

On July 26, the DEP wrote BLCC advising that “The lake has returned to its full capacity with water coming over the spillway. With the unsafe condition of the dam, this situation is unacceptable.” BLCC was instructed to keep the water as low as possible: “Maintaining the conduit in a free flowing state is the responsibility of BLCC… DEP requests BLCC to take active control of the lake and maintain the drawdown as much as possible at all times.”

The DEP set a November 1 deadline for a plan to rehabilitate or remove the dam: “DEP is preparing to breach the dam utilizing Commonwealth resources, as authorized by 25 Pa. Code § 105.62, unless we receive a satisfactory plan for prompt rehabilitation or removal of the dam by November 1, 2013.”  

 

November 1 deadline…

That November 1 deadline has passed, and to our knowledge there has been no plan presented to rehabilitate the dam. As previously reported, we await a decision from the Commonwealth Court on the underlying Third Street litigation– and that litigation has stopped forward progress on the project design. The DEP Division of Dam Safety will have to determine how to proceed to address both the high water level of Broomall’s Lake and the unsafe condition of this high hazard dam.
 

You can read each of the letters from the DEP requesting that the water level be lowered:

– December 23, 2009
– March 28, 2012
– July 2, 2012
– May 10, 2013
– July 26, 2013

You can see the Google Earth images we posted in June, comparing the lake when drawn down in 2010 to the lake at full level in 2011.

]]>
https://glenprovidencepark.org/2013/11/22/update-pa-dep-broomalls-lake-water-level/feed/ 0